A small engineering consulting firm has three senior designers available to work on the firms four current projects over the next two weeks. Each designer

A small engineering consulting firm has three senior designers available to work on
the firms four current projects over the next two weeks. Each designer has eighty
hours to split among the projects, and the following table shows the managers
scoring (0= nil up to 100= perfect) of the capability of each designer to contribute to
each project, along with an estimate of the hours that each project will require.
Designer Project
1234
190801050
260705065
370408085
Required hours 70508535
(i) The manager wants to assign designers to maximize total capability. Formulate a
linear programming problem to help the manager.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transportation A Global Supply Chain Perspective

Authors: Robert A. Novack, Brian Gibson, Yoshinori Suzuki, John J. Coyle

9th Edition

1337406643, 9781337406642

More Books

Students also viewed these General Management questions