A subcontractor that is scheduled to work on a critical project task originally quoted a cost of $5000 with a duration of 9 days. Eager
A subcontractor that is scheduled to work on a critical project task originally quoted a cost of $5000 with a duration of 9 days. Eager to speed up the project, you requested a quote for the fastest the subcontractor could complete the tack. The subcontractor has just replied with a "fastest quote for the project task of 5 days for a cost of $7800. Assuming a linear relationship between the cost and duration of the original quote and the "fastest quote, what would you expect the tack to cost if you wanted it completed in 7days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started