A task is expected to take 20 hours of labor at $25 per hour (direct cost).The required material cost is $500.The organization adds a burden
- A task is expected to take 20 hours of labor at $25 per hour (direct cost).The required material cost is $500.The organization adds a burden of 30% to all direct labor costs to account for overhead.It does not add any burden on top of material costs.The total task cost is: