A wind farm developer has obtained planning permission to build a cluster of nine 3000kW turbine with the following information: Government has scrapped all subsidies

A wind farm developer has obtained planning permission to build a cluster of nine 3000kW turbine with the following information:

Government has scrapped all subsidies for onshore wind, so revenue from the project will come only from sales of electricity to the wholesale electricity market only. Average wholesale electricity prices over the last few years have been around 50 /MWh.

Company profits from the project will be taxed at standard corporation tax rates. Taxable income in any year is net cash flow minus capital expenditure depreciation allowances, i.e. all operating and maintenance costs are tax deductible. Capital expenditure depreciation allowances are calculated from the straight line depreciation of the capital expenditure over the first 6 years of the operation of the turbines, i.e. 1/6 of the development expenditure can be set off against tax in any year. Initial work on site has revealed that there it may be possible to build more than 9 turbines on the site (although planning permission would have to be applied for). The turbines have an expected economic life from 25 years to a maximum of up to 30 years. The government has recently changed the regulations on wind farm decommissioning. The company has estimated that these changes effectively increase decommissioning costs from 5% to 15% of the original capital costs. All decommissioning costs are tax deductible. The company is currently all-equity financed. Currently the company has evaluated the risk free rate of return rate as 3% and the expected return on Market portfolio (FTSE 100 Index) is 10%. The market beta for the Energy Company is 1.2.

Assignment Task

  1. Using the information in Wind-Data.xlsx, build a Spreadsheet model to obtain the NPV (plus any other output values (metrics) you feel are useful) of the wind farm project. (For this case you may ignore inflation and treat all values in the spreadsheet as if they are in real terms)

additional information:

Turbine Capacity (KWh) 3000
Turbine Economic Lifetime (years) 25
Total Hours of Potential Operation (yearly) 8760
Load Factor (% of Potential Time Operated) 30%
Total Cost of Construction () per Turbine 2,800,000
Grid Connnection Costs 1,300,000
Other Capital Costs 2,600,000
Yearly Operation and Maintenance Costs () per Turbine 150,000
Number of Turbines 9
Decommisioning Costs 15%
Inflation 0.50%
Cost of Capital
risk free 3.0%
ftse 10%
beta 1.20
Electricity price 50
Corporate tax rate 0,25
Depreciation allowance years 6

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Valuation A Guide For Managers And Investors

Authors: Phillip R. Daves, Michael C. Ehrhardt, Ron E. Shrieves

1st Edition

0324274289, 978-0324274288

More Books

Students also viewed these Finance questions