According to the defects burnout chart below, please explain whether a product was delivered well or not for sprint 3? Why or why not? Sprint
According to the defects burnout chart below, please explain whether a product was delivered well or not for sprint 3? Why or why not?
Sprint 1 Sprint 2 Sprint 3 Total Total Open Defects 30 12 4 46 Total Closed Defects 20 21 5 46 Percent Complete 43.5% 45.7% 10.9% 100.0% Defects/Issues Low Med High Total Sprint 1 9 4 17 Sprint 2 6 3 3 12 Sprint 3 3 16 8 8 32 32 Remainnig O Defects Severity Chart + Defects Burndown 50 Sprint 1 Sprint 2 0Sprint 3 10 40 Y 8 30 6 O 20 4 10 3 3 0 N Sprint 1 Sprint 2 Sprint 3 Total O Low Med High Total Open Defects Total Closed Defects OStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started