Activity A Activity B Activity D Activity C What is the earliest that Activity D can begin if Activity A takes 3 days, Activity B
Activity A Activity B Activity D Activity C What is the earliest that Activity D can begin if Activity A takes 3 days, Activity B takes 5 days, and Activity C takes 7 days? Ltfen birini sein: A Day 5 B Day 15 C. Day D. Day 8