Activity Description Activity Time Preceding Activity A Problem Definition 2 None B System Analysis 3 A C Design I / Q 4 B D Design
Activity Description Activity Time Preceding Activity
A Problem Definition None
B System Analysis A
C Design IQ B
D Design Database B
E Develop Input Screens C
F Develop Output Reports C
G Create Database D
H Test System E G
I Implement System H
Given the project network information, complete the forward and backward pass. What is early start for Activity I