Question

1 Approved Answer

Activity Duration (week) Precedents A Requirement Analysis 5 - B System design 15 A C Programming 25 B D Telecoms 15 B E Hardware Installation

Activity

Duration

(week)

Precedents
A Requirement Analysis 5 -
B System design 15 A
C Programming 25 B
D Telecoms 15 B
E Hardware Installation 30 B
F Integration 10 C, D
G System Testing 10 E, F
H Training and support 5 G
I Handover and Go-Live 5 H

Using the following table, if the project team will work a standard week work and that all the tasks will start as soon as possible: 1. Draw the corresponding activity network 2. Show the critical path. 3. What is the minimum time required to finish the project? 4. If task C (Programming) is delayed for 2 weeks, will the project finish on time? Why? If task (D Telecoms) is delayed for 2 weeks, will the project finish on time? Why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Marketing The Ultimate Marketing Tool

Authors: Edward L. Nash

1st Edition

0070460639, 978-0070460638

More Books

Students also viewed these Databases questions

Question

If both \ sigma and sx are given, which should be used

Answered: 1 week ago