Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Activity Duration (week) Precedents A Requirement Analysis 5 - B System design 15 A C Programming 25 B D Telecoms 15 B E Hardware Installation
Activity | Duration (week) | Precedents |
A Requirement Analysis | 5 | - |
B System design | 15 | A |
C Programming | 25 | B |
D Telecoms | 15 | B |
E Hardware Installation | 30 | B |
F Integration | 10 | C, D |
G System Testing | 10 | E, F |
H Training and support | 5 | G |
I Handover and Go-Live | 5 | H |
Using the following table, if the project team will work a standard week work and that all the tasks will start as soon as possible: 1. Draw the corresponding activity network 2. Show the critical path. 3. What is the minimum time required to finish the project? 4. If task C (Programming) is delayed for 2 weeks, will the project finish on time? Why? If task (D Telecoms) is delayed for 2 weeks, will the project finish on time? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started