Activity Immediate Predecessor ( s ) Duration ( Weeks ) Activity Duration Immediate Predecessor ( s ) ( Weeks ) 6 A 4 F B

Activity
Immediate Predecessor(s)
Duration (Weeks)
Activity
Duration
Immediate Predecessor(s)
(Weeks)
6
A
4
F
B
C
B
10
7
G
2
C
H
F
8
D
A
5
F, G
11
E
B
3
J
D, E
8
a) Draw a network diagram and find the critical path and project completion time.
b) Calculate float/ slack of the all activities.
c) If $1000 can be saved for each delayed day of activity H, then how much dollar can be saved keeping the project completion time unchanged?
d) Activity G needs a delayed time of two weeks and an extra time of five weeks. Is it possible by keeping the project completion time unchanged? Explain.
e) The PM wants to shorten the duration of the activity I from 11 weeks to 9 weeks. What is the impact of this change on project completion time?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions

Question

What is the difference between visual and spatial imagery?

Answered: 1 week ago