Activity Predecessor Duration A NONE 2 B A 4 C A 3 D A 2 E B 3 F C 6 G C , D

Activity Predecessor Duration
A NONE 2
B A 4
C A 3
D A 2
E B 3
F C 6
G C,D 5
H E,F 6
I G 5
J H,I 5
Part A
Draw a project network diagram from the above information.
Activities B and H can be shortened to a minimum of 2 weeks; which activity would you shorten to reduce the project duration by 2 weeks?
Why?
Explain the risk associated with leveling resources, compressing or crashing projects, and imposed duration(s) or "catch-up" as the project is being implemented.Activity Predecessor Duration
A NONE 2
B A 4
C A 3
D A 2
E B 3
F C 6
G C,D 5
H E,F 6
I G 5
J H,I 5
Part A
Draw a project network diagram from the above information.
Activities B and H can be shortened to a minimum of 2 weeks; which activity would you shorten to reduce the project duration by 2 weeks?
Why?
Explain the risk associated with leveling resources, compressing or crashing projects, and imposed duration(s) or "catch-up" as the project is being implemented.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

More Books

Students also viewed these General Management questions