Question

1 Approved Answer

Actual Results (125,000 units) Materials Fabric 125,000 yds @ $5.50/yd $687,500 Steel tubing 32,000 lbs @ $12.20/lb 390,400 Padding 65,000 lbs @ .49/lb 31,850 Direct

Actual Results

(125,000 units)

Materials

Fabric

125,000 yds @ $5.50/yd

$687,500

Steel tubing

32,000 lbs @ $12.20/lb

390,400

Padding

65,000 lbs @ .49/lb

31,850

Direct Labor

Machining

35,000 hrs @ $18/hr

630,000

Assembly

11,000 hrs @ $11.50/hr

126,500

Overhead

Rent

96,000

Property taxes

10,000

Other Overhead

210,000

Total

$2,182,250

Following is Perry Corporations original budget for 2014, and their actual results for 2014. [24 points]

Original Budget

(100,000 units)

Materials

Fabric

100,000 yds @ $5.40/yd

$540,000

Steel tubing

25,000 lbs @ $12.10/lb

302,500

Padding

50,000 lbs @ $.50/lb

25,000

Direct Labor

Machining

30,000 hrs @ $19/hr

570,000

Assembly

10,000 hrs @ $11.80/hr

118,000

Overhead

Rent

100,000

Property taxes

10,000

Other Overhead

(25% variable)

200,000

Total

$1,865,500

Using the format on the following page, prepare the flexible budget needed to evaluate Perry Corporations performance for 2014, and compute the Flex-Actual Variances. Show your calculations.

Calculations

Flexible Budget

Actual

(125,000 units)

Flex Actual Variances

Materials

Fabric

540,000

$687,500

Steel tubing

302,500

390,400

Padding

25,000

31,850

Direct Labor

Machining

630,000

Assembly

126,500

Overhead

Rent

96,000

Property taxes

10,000

Other Overhead

(25% variable)

210,000

Total

$2,182,250

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting

Authors: Charles T. Horngren, Walter T. Harrison Jr., M. Suzanne Oliv

9th Edition

130898414, 9780132997379, 978-0130898418, 132997371, 978-0132569309

More Books

Students also viewed these Accounting questions

Question

Describe the process of supplier processing in pastel partner

Answered: 1 week ago