Additional Algo 3 - 3 Process Capacity Drivers are trained in a process with two sequential resources. A worker in the first resource trains 0
Additional Algo Process Capacity
Drivers are trained in a process with two sequential resources. A worker in the first resource trains drivers per hour and a worker in the second resource trains drivers per hour. The first resource has workers and the second resource has workers.
What is the capacity of this process in terms of drivers per hour?
Note: Round your answer to decimal places.