Additional Algo 5 - 2 0 Multiple Flow Units Electricians are trained in a process with a single resource. There are two types of electricians.

Additional Algo 5-20 Multiple Flow Units
Electricians are trained in a process with a single resource. There are two types of electricians. The resource's processing time for the first type is 33 hours and demand for this type is 0.037 electricians per hour. The resource's processing time for the second type is 23 hours and demand for this type is 0.052 electricians per hour. There are 2 workers at this resource.
What is the implied utilization (%) of this resource?
Note: Round your answer to 1 decimal place.
Implied utilization
8.0%
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions