Again, the diagram begins and ends with circles labeled START and END. The drawing standards are the same here as before. For each task, the
Again, the diagram begins and ends with circles labeled START and END. The drawing standards are the same here as before. For each task, the Task Name is placed above a line and the task duration is placed below the line. Since there are four tasks which can begin immediately, four arrows are drawn from the START circle to indicate Tasks ABC and D
In this example, you now see a task that has multiple more than one predecessor, eg Task E has two predecessors, A and B In this case, use a circle to denote the end of both tasks A and B Do this by drawing a Circle labeled and connecting the arrows labeled A and B to it refer to the diagram above Then you can draw a line originating from Circle representing Task E
Repeat this for Tasks F and G and you should be able to recreate the diagram above. Notice that the Critical Path for this project is BEG, and the duration of the critical path is weeks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started