Again, the diagram begins and ends with circles labeled START and END. The drawing standards are the same here as before. For each task, the

Again, the diagram begins and ends with circles labeled START and END. The drawing standards are the same here as before. For each task, the Task Name is placed above a line and the task duration is placed below the line. Since there are four tasks which can begin immediately, four arrows are drawn from the START circle to indicate Tasks "A,""B,""C," and "D."
In this example, you now see a task that has multiple (more than one) predecessor, e.g. Task "E" has two predecessors, "A" and "B." In this case, use a circle to denote the end of both tasks "A" and "B". Do this by drawing a Circle labeled 1 and connecting the arrows labeled A and B to it (refer to the diagram above). Then you can draw a line originating from Circle 1 representing Task "E."
Repeat this for Tasks "F" and "G", and you should be able to recreate the diagram above. Notice that the Critical Path for this project is BEG, and the duration of the critical path is 9 weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions