(AICPA) Dream Construction Company has consistently used the percentage-of-completion method of recognizing income. During 2021, it entered into a fixed price contract to construct an

(AICPA) Dream Construction Company has consistently used the percentage-of-completion method of recognizing income. During 2021, it entered into a fixed price contract to construct an office building for P10,000,000. Information relating to the contract is as follows:

12/31/21

12/31/22

Percentage of completion

20%

60%

Estimated total cost at completion

P7,500,000

P8,000,000

Gross profit recognized (cumulative)

500,000

1,200,000

Contract costs incurred during 2022 were

a. 3,300,00

b 3,200,000

c. 3,500,000

d. 4,800,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting A Managerial Emphasis

Authors: Charles T. Horngren, Srikant M.Dater, George Foster, Madhav

13th Edition

8120335643, 136126634, 978-0136126638

More Books

Students also viewed these Accounting questions

Question

1. 5. What is meant by present bias?

Answered: 1 week ago