Answered step by step
Verified Expert Solution
Question
1 Approved Answer
An activity on a PERT network has these time estimates: optimistic = 1.6, most likely = 5.4, and pessimistic = 10. What is its expected
An activity on a PERT network has these time estimates: optimistic =
1.6,
most likely =
5.4,
and pessimistic = 10. What is its expected activity time and
variance?
(Do not round intermediate calculations. The round final answer to two decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started