An article in Communications of the ACM (Vol. 30, No. 5, 1987) studied different algorithms for estimating software development costs. Six algorithms were applied to
An article in Communications of the ACM (Vol. 30, No. 5, 1987) studied different algorithms for estimating software development costs. Six algorithms were applied to several different software development projects and the percent error in estimating the development cost was observed. Some of the data from this experiment is shown in the table below.
Algoritm | 1 | 2 | 3 | 4 | 5 | 6 |
1(SLIM) | 1244 | 21 | 82 | 2221 | 905 | 839 |
2(COCOMO-A) | 281 | 129 | 396 | 1306 | 336 | 910 |
3(COCOMO-R) | 220 | 84 | 458 | 543 | 300 | 794 |
4(COCOMO-C) | 225 | 83 | 425 | 552 | 291 | 826 |
5(FUNCTION POINTS) | 19 | 11 | -34 | 121 | 15 | 103 |
6(ESTIMALS) | -20 | 35 | -53 | 170 | 104 | 199 |
1. Do the algorithms differ in their mean cost estimation accuracy?
2. Analyze the residuals from this experiment.
3. Which algorithm would you recommend for use in practice? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started