Question

1 Approved Answer

An assembly line currently has five workstations, and the time required for each is shown in the figure below. Workstation 1 2 3 4 5

An assembly line currently has five workstations, and the time required for each is shown in the figure below.
Workstation 1 2 3 4 5
Time required (Seconds) 46 35 50 37 32
Required:
Note: Use cell A2 to F5 from the given information to complete this question.
a. What is the efficiency of the current process? Hint: Identify the bottleneck work station.
Note: Use cell A13 to B14 from the given information to complete this question. Round up your answer to the next whole number.
Bottleneck station 50
Number of stations 5
Efficiency
b. Customer demand is 80 units per hour. What is the hourly production rate of the current process?
Note: Use cell A21 to B22 from the given information to complete this question.
Minutes per Hour 60
Seconds per Minute 60
Current hourly production
c. What does the takt time need to be able to meet demand?
Note: Use row 29 from the given information to complete this question.
Demand (units/hour) 80
Takt time needed (seconds/station)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Theory And Practice

Authors: John A. Parnell

4th Edition

1452234981, 9781452234984

More Books

Students also viewed these General Management questions