An assembly line currently has five workstations, and the time required for each is shown in the figure below. Workstation 1 2 3 4 5
An assembly line currently has five workstations, and the time required for each is shown in the figure below. | ||||||
Workstation | 1 | 2 | 3 | 4 | 5 | |
Time required (Seconds) | 46 | 35 | 50 | 37 | 32 | |
Required: | ||||||
Note: Use cell A2 to F5 from the given information to complete this question. | ||||||
a. What is the efficiency of the current process? Hint: Identify the bottleneck work station. | ||||||
Note: Use cell A13 to B14 from the given information to complete this question. Round up your answer to the next whole number. | ||||||
Bottleneck station | 50 | |||||
Number of stations | 5 | |||||
Efficiency | ||||||
b. Customer demand is 80 units per hour. What is the hourly production rate of the current process? | ||||||
Note: Use cell A21 to B22 from the given information to complete this question. | ||||||
Minutes per Hour | 60 | |||||
Seconds per Minute | 60 | |||||
Current hourly production | ||||||
c. What does the takt time need to be able to meet demand? | ||||||
Note: Use row 29 from the given information to complete this question. | ||||||
Demand (units/hour) | 80 | |||||
Takt time needed (seconds/station) | ||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started