Question

1 Approved Answer

An XP team is notified that an important server upgrade will be delayed by six months due to budget constraints. The upgrade included several important

An XP team is notified that an important server upgrade will be delayed by six months due to budget constraints. The upgrade included several important features that their plan depended on, and the delay will require two team members to spend three entire weekly cycles on a workaround. How should the team account for this?
Track the work done by the two team members separately from the rest of the project work
Update the release plan to reflect the change in the team's capacity to work on main deliverables
Use a risk-based spike to reduce the uncertainty
Expect the velocity to be reduced and update the release plan accordingly
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Data Management Databases And Organizations

Authors: Watson Watson

5th Edition

0471715360, 978-0471715368

More Books

Students also viewed these Databases questions