Question
Ann is invited to help an Agile Release Train (ART) that is struggling. They just finished the second Iteration in the Program Increment (PI) and
Ann is invited to help an Agile Release Train (ART) that is struggling. They just finished the second Iteration in the Program Increment (PI) and have nothing to demonstrate at the System Demo. What steps might Ann recommend?
Program stakeholders are really concerned. What should Ann do?
A: Re-architect the system so that there are no dependencies between the teams, and integration is not needed
B: Have every team demonstrate their team increment to the stakeholders separately in the team branch
C: Stop working on any new functionality and fully integrate and test the system; adjust scope based on learnings
D: Continue to work on new functionality and reserve time to fully integrate the system during the IP Iteration.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started