Answer all questions below in an Excel spreadsheet. Put each task on a separate worksheet. In cells that contain calculated values, use Excel's formulas and/or functions so I can see how you came up with your results. Be sure to complete all three tasks. Task 1 The diagram below is a partial WBS for a tablet computer project with costs apportioned by percent. Given that the total project cost is estimated to be $1,000,000, provide the estimated costs for each item. E-Slim Tablet Cost: $1,000,000 CPU Hardware 40% 60% Cameras Antenna Frame 10% Speakers 10% Flash ROM 10% Power Supply 20% 10% 1/0 Controller 25% 15% Format your worksheet like this (use a formula to calculate the estimated cost in column B): Estimated cost Deliverable Hardware Frame Cameras Speakers Antenna CPU Power Supply Flash ROM 1/ Controller Task 2 Using the "complexity weighting" scheme shown in Table 5.2 (p. 138) and the function point complexity weighted table shown below, estimate the total function point count for this project. Assume historical data suggests that seven function points equal one personi a month and five people can work on the project. Your table should look similar to the bottom part of Table 5.3 (p. 139). Where possible, be sure to use formulas. Underneath your table, respond to the following questions: a. What is the estimated project duration? b. If 9 people are available for the project, what is the estimated project duration to the nearest tenth)? c. If the project must be completed in 6 months, how many people are needed for the project to the nearest tenth)? 20 Complexity Weight Table Number of inputs Number of outputs Number of inquiries Number of files Number of interfaces 10 15 20 10 Rated complexity average Rated complexity high Rated complexity low Rated complexity average Rated complexity high