Answer questions 1 to 4 based on the following information: Medro and Mariana have just finished carrying out the CPM method on their south east

Answer questions 1 to 4 based on the following information:

Medro and Mariana have just finished carrying out the CPM method on their south east Asia project as shown below. Answer the questions based on the table and network diagram. The times are in units of days.
1
The minimum time to finish the project in normal time is?
a. 37 days
b. 29 days
c. 45 days
d. 47 days
2
Is J critical?
a. Yes
b. No
c. Maybe
d. Not enough information to answer question
3
By how much can D be delayed without delaying the project?
a. 2 days
b. 20 days
c. 27 days
d. Not enough information to answer the question
4
If Medro & Mariana wish to crash the project by 9 days. Which activities must be crashed and what will the total crashing cost be?
a. crash C by 4 days & E by 5 days. Total crashing cost = 125 KD
b. crash C by 4 days & E by 4 days & I by 1 day. Total crashing cost = 135 KD
c. crash C by 4 days & I by 2 days & E by 3 days. Total crashing cost = 130 KD
d. none of the above

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Nonprofit Management Principles and Practice

Authors: Michael J. Worth

4th edition

1483375994, 978-1483375991

More Books

Students also viewed these General Management questions

Question

identify ways of measuring and accounting for externalities

Answered: 1 week ago