Question
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs.
Job 102 Job 103 Job 104
Direct materials $ 44,000 $ 54,000 $ 53,000
Direct labor 16,000 30,000 41,000
Overhead applied 5,280 9,900 13,530
Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $11,000; direct labor, $3,400; and overhead, $1,122.
Jobs 103 and 104 were started in June. Overhead cost is applied with a predetermined rate based on direct labor cost.
Jobs 102 and 103 were finished in June, and Job 104 is expected to be finished in July.
No raw materials were used indirectly in June. Using this information, answer the following questions. (Assume this company’s predetermined overhead rate did not change across these months.)
1&2. Complete the table below to calculate the cost of the raw materials.
3. Using the accumulated costs of the jobs, what predetermined overhead rate is used?
4. How much total cost is transferred to finished goods during June?
Step by Step Solution
3.32 Rating (152 Votes )
There are 3 Steps involved in it
Step: 1
Predetermined overhead rate Overhead applied Direct labor Job 102 Predetermined overhead rate 5...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started