As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output

As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:

TaskDuration

Task Duration

(minutes) Immediate

Predecessor a 0.2 b 0.4 a c 0.2 b d 0.4 e 1.2 d f 1.2 c g 1.0 e, f

c.Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.

d.Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation.(Round your answer to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Psychology Applied To Teaching

Authors: Jack Snowman, Rick McCown

14th Edition

1285734556, 9781285734552

More Books

Students also viewed these Accounting questions