Question
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:
Task | Duration (minutes) | Immediate Predecessor |
a | 0.2 | - |
b | 0.4 | a |
c | 0.2 | b |
d | 0.4 | - |
e | 1.2 | d |
f | 1.2 | c |
g | 1.0 | e, f |
d. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.
Answer:
Work stations | Following Tasks |
I | A, B, D, C |
II | E |
III | F |
IV | G |
e. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation. (Round your answer to 2 decimal places. Omit the "%" sign in your response.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started