As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output

As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:

Task Duration (minutes) Immediate Predecessor
a 0.2 -
b 0.4 a
c 0.2 b
d 0.4 -
e 1.2 d
f 1.2 c
g 1.0 e, f

d. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.

Answer:

Work stations Following Tasks
I A, B, D, C
II E
III F
IV G

e. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation. (Round your answer to 2 decimal places. Omit the "%" sign in your response.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Principles Volume 1

Authors: Jerry J. Weygandt, Donald E. Kieso, Paul D. Kimmel, Barbara Trenholm, Valerie Warren, Lori Novak

9th Canadian Edition

978-1119786818, 1119786819

More Books

Students also viewed these Accounting questions