Question

1 Approved Answer

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2013 and was completed in 2014. Data relating

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2013 and was completed in 2014. Data relating to the contract are summarized below:

2013 2014
Costs incurred during the year $ 300,000 $ 1,575,000
Estimated costs to complete as of 12/31 1,200,000 0
Billings during the year 380,000 1,620,000
Cash collections during the year 250,000 1,750,000

Required:
1.

Compute the amount of gross profit or loss to be recognized in 2013 and 2014 using the percentage-of-completion method.

2.

Compute the amount of gross profit or loss to be recognized in 2013 and 2014 using the completed contract method.

3.

Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2013 using the percentage-of-completion method.

4.

Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2013 using the completed contract method.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting For OHADA Member States Volume 1

Authors: Michael Forzeh Fossung

1st Edition

3330328037, 978-3330328037

More Books

Students also viewed these Accounting questions