Question
Assume that a project is at the end of the fourth month with a 75% rate of performance with $ 550,000.0 Actual Cost and
Assume that a project is at the end of the fourth month with a 75% rate of performance with $ 550,000.0 Actual Cost and $ 400,000.0 Planned Cost Value. The BAC (budget at completion) was $950, 000 for this one-year project. (6 points) (SO 02) 1. Calculate the estimate at completion (EAC) for this project? (2 points) 2. Estimate how long it will take to finish this project? (2 points) 3. How is the project doing concening schedule and budget? (2 points) Attach your answer in handwritten format with the permitted types of files.
Step by Step Solution
3.45 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
1Calculate the estimate at completion for this budget Actual costAC 550000 Planne...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Project Management A Managerial Approach
Authors: Jack R. Meredith, Samuel J. Mantel,
7th Edition
470226218, 978-0470226216
Students also viewed these Computer Network questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App