Question

1 Approved Answer

Assume that a project is at the end of the fourth month with a 75% rate of performance with $ 550,000.0 Actual Cost and

 

Assume that a project is at the end of the fourth month with a 75% rate of performance with $ 550,000.0 Actual Cost and $ 400,000.0 Planned Cost Value. The BAC (budget at completion) was $950, 000 for this one-year project. (6 points) (SO 02) 1. Calculate the estimate at completion (EAC) for this project? (2 points) 2. Estimate how long it will take to finish this project? (2 points) 3. How is the project doing concening schedule and budget? (2 points) Attach your answer in handwritten format with the permitted types of files.

Step by Step Solution

3.45 Rating (155 Votes )

There are 3 Steps involved in it

Step: 1

1Calculate the estimate at completion for this budget Actual costAC 550000 Planne... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these Computer Network questions

Question

Find three errors in the diagrambelow. 9. 5.

Answered: 1 week ago