Assume that the following occurred when executing the project. Scenario 25% timeline The project sponsor wants to add a new feature contact pages to the

Assume that the following occurred when executing the project.

Scenario

25% timeline

The project sponsor wants to add a new feature "contact pages" to the website.

The new deliverable will take 2 additional weeks to be completed.

The PSC is willing to provide an additional $5,000.

The PM has been told not to add any other staff to the project team.

  1. For this scenario:

  • Detail what the project schedule monitoring and control procedures applied to identify the issue/s
  • Outline how the issues are addressed to minimise the impact on the project schedule and maintain project objectives
  • Determine any schedule baseline variance

Monitoring and control

(30 50 words/scenario)

How the issue was addressed

(40 80 words/scenario)

Variance to the schedule baseline

Change request process

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: Richard Lynch , Oliver Barish Barish , Vinh Sum Chau , Charles Thornton , Karl S. R. Warner

10th Edition

1529672554, 978-1529672558

More Books

Students also viewed these General Management questions

Question

Does a monopolist have a supply curve? Briefly explain.

Answered: 1 week ago

Question

9. Identify some of the current trends in operations management.

Answered: 1 week ago