Assume you plan to make boxes just by yourself now. We will not make lids for the boxes this time. Then the stages to make

Assume you plan to make boxes just by yourself now. We will not make lids for the boxes this time. Then the stages to make a box should be (in this order)

A: Fold horizontally and vertically, unfold, B: Fold four corners, C: Fold sides to center, D: Unfold two sides and reverse fold them to finish. Assume the following amount of work in seconds is required at each station: A: 30 secs, B: 32 secs, C: 46 secs, and D: 58 secs. (Assume you want to make many boxes, i.e., perform the calculations for a continuous process.)

1. What is the capacity rate of your process (boxes per hour)? (Keep two decimal places.)

2. What is the cycle time of your process (secs)?

3. What is your utilization?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

1 To calculate the capacity rate we need to first determine the bottleneck station This is the stati... blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Engineering economy

Authors: Leland Blank, Anthony Tarquin

7th Edition

9781259027406, 0073376302, 1259027406, 978-0073376301

More Books

Students explore these related General Management questions