At Countrywide Construction, you are trying to convince your boss that he should consider modern project management techniques to manage a complex project. Your boss
At Countrywide Construction, you are trying to convince your boss that he should consider modern project management techniques to manage a complex project. Your boss says that he doesnt need anything fancy and that he can guess the total time by the seat of his pants. To prove your point, you decide to use a very simple example of a commercial construction project with 8 tasks. You create a hypothetical work breakdown structure as follows:
Prepare the foundation (10 days). Then assemble the building (4 days)
When building is assembled start 2 tasks at once: Finish the interior work (4 days) and set up appointment for the final building inspection (30 days).
When the interior work is done, start 2 more tasks at once: Landscaping (5 days) and driveway paving(2days)
When the landscaping and driveway are done do the painting (5 days)
Finally when the painting is done and the final inspection has occurred, arrange the sale (3 days)
Now you ask your boss to estimate the total time and write his answer on a piece of paper. You look at the paper and aee that his guess was wrong.
1. What is the correct answer?
2. What is the critical path?
3. Create a Grantt chart that shows the WBS.
4. Create a PERT?CPM chart.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started