At the beginning of the period, the Cutting Department budgeted direct labor of $155,000, direct materials of $165,000, and fixed factory overhead of $15,000 for
At the beginning of the period, the Cutting Department budgeted direct labor of $155,000, direct materials of $165,000, and fixed factory overhead of $15,000 for 9,000 hours of production. The department actually completed 10,000 hours of production. What is the appropriate total budget for the department, assuming it uses flexible budgeting?
a. $370,556 b. $416,000 c. $335,000 d. $368,889