Question

1 Approved Answer

A+UM+ Question 1) Activity Predecessor Optimistic Most Pessimistic Likely A 5 7 15 B 14 21 22 C 21 33 45 D A 14

image text in transcribed

A+UM+ Question 1) Activity Predecessor Optimistic Most Pessimistic Likely A 5 7 15 B 14 21 22 C 21 33 45 D A 14 16 30 E B 18 19 26 F B 7 9 11 G B. C 7 9 17 D 8 8 8 I D, E 3 4 5 F. G 4 5 6 K H. I 7 8 21 a) (10 points) Develop an AOA diagram for the given activities. b) (5 points) Find the critical path and project completion time. c) (10 points) Find the probability of completing the project at 58 days. d) (10 points) The project manager is promised $12,000 if the project completed in less than 50 days, $8,000 if the project completed within 50-53 days, and no reward if the project goes above 53 days. What is the expected value of the manager's bonus?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

Students also viewed these General Management questions