Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A+UM+ Question 1) Activity Predecessor Optimistic Most Pessimistic Likely A 5 7 15 B 14 21 22 C 21 33 45 D A 14
A+UM+ Question 1) Activity Predecessor Optimistic Most Pessimistic Likely A 5 7 15 B 14 21 22 C 21 33 45 D A 14 16 30 E B 18 19 26 F B 7 9 11 G B. C 7 9 17 D 8 8 8 I D, E 3 4 5 F. G 4 5 6 K H. I 7 8 21 a) (10 points) Develop an AOA diagram for the given activities. b) (5 points) Find the critical path and project completion time. c) (10 points) Find the probability of completing the project at 58 days. d) (10 points) The project manager is promised $12,000 if the project completed in less than 50 days, $8,000 if the project completed within 50-53 days, and no reward if the project goes above 53 days. What is the expected value of the manager's bonus?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started