Question
Baingana pool builders installs residential swimming pools and uses a job costing system with two direct cost categories and one overhead cost pool. Direct labor
Baingana pool builders installs residential swimming pools and uses a job costing system with two direct cost categories and one overhead cost pool. Direct labor hours is the cost driver for overhead costs. For 2011, the company budgeted overhead costs to be $7,000,000 and estimated direct labor hours at 175,000. At the end of 2011, the company is comparing the costs of several jobs started and completed this year.
Job1 Job 2
Direct Materials $100,000 $125,000
Direct Labor $ 35,000 $ 40,000
Direct Labor hours 900 1100
Building period may-june may-july
Direct materials and direct labor are contracted before the pools are installed. The 2011 overhead costs were $7,200,000 and the actual direct labor hours in 2011 were 160,000.
a. compute budgeted overhead rate and actual indirect cost rate
b. Compute the overhead costs for each job using a) normal costing and b.) actual costing
d. compute the costs of both jobs using a) normal costing and b.) actual costing
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started