Based on the table below, perform resource-limited scheduling. Assume that each task can be performed independently of the other tasks. Also, assume that only 3
Based on the table below, perform resource-limited scheduling. Assume that each task can be performed independently of the other tasks. Also, assume that only 3 workers are available at any given time. What is the new completion date for the project?
Task | Workers Needed | Schedule days |
1 | 3 | 1,2,3 |
2 | 22 | 1,2,3,4 |
3 | 1 | 1,2,3,4 |
4 | 2 | 5,6,7 |
5 | 3 | 6,7,8 |
6 | 1 | 6,7 |