Question
1 Approved Answer
Below are the optimistic (a), most likely (m) and pessimistic (b) times (in days) for the activities on the critical path for a large project.
Below are the optimistic (a), most likely (m) and pessimistic (b) times (in days) for the activities on the critical path for a large project.
TASK | a | m | b |
A | 4 | 15 | 17 |
B | 7 | 12 | 21 |
C | 3 | 6 | 13 |
D | 6 | 14 | 27 |
E | 18 | 27 | 29 |
Copy data into Excel.
(a) Find the project (critical path) expected time and standard deviation.
(b) Find the probability of the project (critical path) being completed in 70 days.
(c) How many days should be allocated to by 95% certain the project will be completed?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started