Question

1 Approved Answer

Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $630,000, what are the estimated

image text in transcribedimage text in transcribed

Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $630,000, what are the estimated costs for the following deliverables? (Round the final answers to the nearest dollar.) b Definition 10% Router systems project $630,000 Design 39% Implementation 51% Objectives Requirements Inputs Outputs Files Interfaces Programming In-house testing Customer testing and review 3% 7% 2% 4% 5% 10% 18% 41% 10% Design? Programming? In-house testing?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Engineering Economy

Authors: Leland T. Blank, Anthony Tarquin

8th edition

978-0073523439

Students also viewed these Accounting questions

Question

Evaluate and simplify the following derivatives. d dw -(e-w In w)

Answered: 1 week ago

Question

What are bonds? AppendixLO1

Answered: 1 week ago

Question

Identify three examples of unearned revenues. AppendixLO1

Answered: 1 week ago