Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $630,000, what are the estimated
Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $630,000, what are the estimated costs for the following deliverables? (Round the final answers to the nearest dollar.) b Definition 10% Router systems project $630,000 Design 39% Implementation 51% Objectives Requirements Inputs Outputs Files Interfaces Programming In-house testing Customer testing and review 3% 7% 2% 4% 5% 10% 18% 41% 10% Design? Programming? In-house testing?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started