BEN REPAIR CENTER JOB JOB TIME (DAYS) DAYS UNTIL DUE A 10 29 B 5 9 C 9 23 D 11 39 E 8 25
BEN REPAIR CENTER
JOB | JOB TIME (DAYS) | DAYS UNTIL DUE |
A | 10 | 29 |
B | 5 | 9 |
C | 9 | 23 |
D | 11 | 39 |
E | 8 | 25 |
F | 7 | 14 |
1) Determine the sequence that BEN should follow if he uses the following two priority rules - EDD (Earliest Due Date) and LPT (Longest Processing Time).
2) Based on the sequence developed for LPT, calculate the following performance measures (NOTE: Please round your calculations to two decimal places). Makespan Mean job flowtime Average number of jobs in the system Mean job lateness Mean job tardiness Job
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started