Benita Hube is the project manager at a printing company. Her assistant has collected the following information for the Colour Printer Drivers Software Project: ID

Benita Hube is the project manager at a printing company. Her assistant has collected the following information for the Colour Printer Drivers Software Project:

ID Description Predecessor Time (Days)
A Develop specifications None 6
B Review design features A 4
C Document new features A 8
D Write software A 55
E Program and test B 35
F Edit and publish notes C 3
G Review manual D 3
H Alpha site E, F 18
I Print manual G 12
J Beta site H, I 12
K Manufacture J 14
L Release and ship K 3

Prepare a project network using AON method (3 Marks)

Compute the early, late, and slack activity times (2 Marks)

Determine the planned project duration(2 Marks)

Identify the critical path (2 Marks)

Identify the Non-Critical activities and discuss the consequences to the overall project if these activities are delayed (3 Marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Analysis For Management

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

11th Edition

9780132997621, 132149117, 132997622, 978-0132149112

More Books

Students also viewed these General Management questions

Question

=+ At what rate does capital per person grow?

Answered: 1 week ago