Benita Hube is the project manager at a printing company. Her assistant has collected the following information for the Colour Printer Drivers Software Project: ID
Benita Hube is the project manager at a printing company. Her assistant has collected the following information for the Colour Printer Drivers Software Project:
ID | Description | Predecessor | Time (Days) |
A | Develop specifications | None | 6 |
B | Review design features | A | 4 |
C | Document new features | A | 8 |
D | Write software | A | 55 |
E | Program and test | B | 35 |
F | Edit and publish notes | C | 3 |
G | Review manual | D | 3 |
H | Alpha site | E, F | 18 |
I | Print manual | G | 12 |
J | Beta site | H, I | 12 |
K | Manufacture | J | 14 |
L | Release and ship | K | 3 |
Prepare a project network using AON method (3 Marks)
Compute the early, late, and slack activity times (2 Marks)
Determine the planned project duration(2 Marks)
Identify the critical path (2 Marks)
Identify the Non-Critical activities and discuss the consequences to the overall project if these activities are delayed (3 Marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started