Question

1 Approved Answer

Best Tech is an innovative technology firm that specializes in developing advanced cybersecurity solutions. The company has embarked on a high - profile project to

Best Tech is an innovative technology firm that specializes in developing advanced cybersecurity solutions. The company has embarked on a high-profile project to develop an AI-powered intrusion detection system, which is critical to its strategic goals. The project's success is crucial for Best Tech to establish itself as a leader in the cybersecurity space.

Project Details:

* Total Budget at Completion (BAC): $2,000,000

* Project Duration: 18 months

* The project is divided into four key phases: Research, Development, Testing, and Deployment.

Situation:

After 9 months into the project, the following data has been reported:

* Planned Value (PV): $1,000,000 (assuming a linear distribution of costs over time)

* Actual Cost (AC): $1,200,000 (actual expenditure at the end of month 9)

* Earned Value (EV): $800,000 (value of work actually accomplished, which is less than planned)

Assumptions:

* The project has been progressing linearly, meaning that the PV accumulates evenly over the project duration.

* Best Tech has a fixed-price contract with the client for the delivery of the system, so any cost overruns will impact the company's profit margins.

EVM Analysis:

Using the standard EVM formulas, we can calculate the following:

* Cost Variance (CV) = EV - AC

* Schedule Variance (SV) = EV - PV

* Cost Performance Index (CPI) = EV / AC

* Schedule Performance Index (SPI) = EV / PV

Discussion Questions:

*  Calculate the CV, SV, CPI, and SPI for the project. What do these values indicate about the current status of the project?

*  Based on the EVM metrics, discuss the potential impact on the project's schedule and budget if current trends continue.

*  Identify at least three potential causes for the discrepancies in the project's performance.

*  As a strategic project manager, how would you approach recovering this project's trajectory?

*  Propose strategies for improving the project's performance and ensuring that the final phase is completed within the original budget and timeline.

 

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Based on the provided project details and data we can answer the questions as follows 1 Calculate the CV SV CPI and SPI for the project What do these ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring Engineering An Introduction to Engineering and Design

Authors: Philip Kosky, George Wise, Robert Balmer, William Keat

2nd edition

123747235, 123747236, 978-0123747235

More Books

Students also viewed these General Management questions

Question

Is it defeatist or useful to focus on adaptive capacity?

Answered: 1 week ago

Question

Solve each equation. x 3 - 6x 2 = -8x

Answered: 1 week ago