Blossom Construction Company uses the percentage-of-completion method. During 2018, the company entered into a fixed-price contract to construct a building for Sherman Company for $46100000.
Blossom Construction Company uses the percentage-of-completion method. During 2018, the company entered into a fixed-price contract to construct a building for Sherman Company for $46100000. The following details pertain to the contract:
At December 31, 2018At December 31, 2019Percentage of completion30%65%Estimated total cost of contract$36950000$39900000Gross profit recognized to date23500003700000
The amount of construction costs incurred during 2019 was
$2950000.
$6800000.
$25935000.
$14850000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started