Question

1 Approved Answer

Blossom Construction Company uses the percentage-of-completion method. During 2018, the company entered into a fixed-price contract to construct a building for Sherman Company for $46100000.

Blossom Construction Company uses the percentage-of-completion method. During 2018, the company entered into a fixed-price contract to construct a building for Sherman Company for $46100000. The following details pertain to the contract:


At December 31, 2018At December 31, 2019Percentage of completion30%65%Estimated total cost of contract$36950000$39900000Gross profit recognized to date23500003700000

The amount of construction costs incurred during 2019 was





$2950000.

$6800000.

$25935000.

$14850000.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Tools for Business Decision Making

Authors: Paul D. Kimmel, Jerry J. Weygandt, Donald E. Kieso, Barbara Trenholm, Wayne Irvine

6th Canadian edition

1118644948, 978-1118805084, 1118805089, 978-1118644942

More Books

Students also viewed these Accounting questions

Question

Discuss Primarks decision to bypass e-commerce.

Answered: 1 week ago