Question
1 Approved Answer
Budgeted direct labour cost : 75 000 hours @ $20 per hour; Actual direct labour cost: 70 000 hours @ $22 per hour; Budgeted manufacturing
Budgeted direct labour cost : 75 000 hours @ $20 per hour; Actual direct labour cost: 70 000 hours @ $22 per hour; Budgeted manufacturing overhead:$980, 000;Actual manufacturing overhead: $950,000
Calculate the overapplied or underapplied overhead for the year.
a.
$38,000
b.
$30,000
c.
$33,000
d.
None of the answersgiven
Clear my choice