Question
Inc. uses activity-based costing to account for its chrome bumper manufacturing process. Company managers have identified four manufacturing activities: materials handling, machine setup, insertion of
Inc. uses activity-based costing to account for its chrome bumper manufacturing process. Company managers have identified four manufacturing activities: materials handling, machine setup, insertion of parts, and finishing. The budgeted activity costs for 2018 and their allocation bases are as follows:
COMPLETE ONLY REQUIREMENT 2
Requirement 1. Compute the predetermined overhead allocation rate for each activity.
Begin by selecting the formula to calculate the predetermined overhead (OH) allocation rate. Then enter the amounts to compute the allocation rate for each activity. (Round your answers to the nearest cent.)
|
|
|
|
|
| Predetermined OH | |
| Estimated overhead costs | / | Estimated qty of the allocation base | = | allocation rate |
Materials handling | $12,000 | / | 4,000 | = | $3.00 |
Machine setup | $3,100 | / | 10 | = | $310.00 |
Insertion of parts | $42,000 | / | 4,000 | = | $10.50 |
Finishing | $86,000 | / | 1,000 | = | $86.00 |
Requirement 2. Compute the expected indirect manufacturing cost of each bumper.
Begin by selecting the formula to allocate overhead (OH) costs.
Predetermined OH allocation rate | x | Expected qty of the allocation base used | = | Allocated mfg. overhead costs |
Now compute the expected indirect manufacturing cost of each bumper. (Round the cost per bumper to the nearest cent.)
| Allocated Mfg. OH Cost |
Materials handling |
|
Machine setup |
|
Insertion of parts |
|
Finishing |
|
Total mfg. OH costs | |
Number of bumpers | 500 |
Mfg. OH cost per bumper | $286.20 |
Activity Total Budgeted Cost Allocation Base Materials handling 12,000 Number of parts Machine setup 3,100 Number of setups Insertion of parts 42,000 Number of parts 86,000 Finishing Finishing direct labor hours 143,100 Total Franklin expects to produce 500 chrome bumpers during the year. The bumpers are expected to use 4,000 parts, require 10 setups, and consume 1,000 hours of finishing time.
Step by Step Solution
3.45 Rating (148 Votes )
There are 3 Steps involved in it
Step: 1
Answer Requirements 1 Compute the predetermined overhead allocation rate for each activity 2 Compute ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
635e371038cb0_182421.pdf
180 KBs PDF File
635e371038cb0_182421.docx
120 KBs Word File