1 Approved Answer
Calculate its critical path and project completion time. table[[ACTIVITY,NODES,TIME (WEEKS)],[J, 1-2 ,10],[K, 1-3 ,8],[L, 2-4 ,6],[M, 2-3 ,3],[N, 3-4 ,2],[O, 4-5 ,7],[P, 3-5 ,5]] Calculate
Calculate its critical path and project completion time.\ \\\\table[[ACTIVITY,NODES,TIME (WEEKS)],[J,
1-2
,10],[K,
1-3
,8],[L,
2-4
,6],[M,
2-3
,3],[N,
3-4
,2],[O,
4-5
,7],[P,
3-5
,5]]