Calculate the NPV of a project that has an outlay of $300,000 and has annual net cash flows of $50000 per year over 9 years.

Calculate the NPV of a project that has an outlay of $300,000 and has annual net cash flows of $50000 per year over 9 years. The project has a salvage value (disposal value) of 10% of its original value. The required rate of return for projects of similar risk is 0.11.

Note that the rate of return is quoted as a decimal, e.g. 12% p.a. is written as .12 in the question above. Your answer must be accurate to the nearest dollar. Do not enter the $ sign when entering your answer. If your NPV is negative enter a minus sign before typing your answer, e.g. -2345.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Financial Management

Authors: Cheol Eun, Bruce G. Resnick

8th edition

125971778X, 978-1259717789

More Books

Students also viewed these Finance questions