Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Calculate the NPV of each alternative based in originally projected costs and savings? Conduct quantitative sensitivity based on the ranges of possible cost estimates? Assess

  1. Calculate the NPV of each alternative based in originally projected costs and savings?
  2. Conduct quantitative sensitivity based on the ranges of possible cost estimates?
  3. Assess the qualitative risks and rewards of proceeding with this project, and each alternative?
image text in transcribed As a financial analyst at the Lunchbox Music Studio, you have been asked to evaluate two capital investment alternatives. The company policy has set the cost of capital at \15 for all proposed projects. Lunchbox's usual corporate tax rate is \35. The proposed capital project calls for developing new computer software to facilitate partially automating the sound engineering for recording. Alternative A has initial software development costs projected at \\( \\$ 194,000 \\), while Alternative B would cost \\( \\$ 336,000 \\). Software development costs would be capitalized and qualify for a capital cost allowance (CCA) rate of \30. In addition, IT would hire a software consultant under either alternative to assist in making the decision whether to invest in the project for a fee of \\( \\$ 17,000 \\) and this cost would be expensed when it is incurred. To recover its costs, Lunchbox's IT department would charge the production department for the use of computer time at the rate of \\( \\$ 394 \\) per hour and estimates that it would take 182 hours of computer time per year to run the new software under alternative. Lunchbox owns all its computers and does not currently operate them at capacity. The IT plan calls for this excess capacity to continue in the future. For security reasons, it is company policy not to rent excess computing capacity to outside users. If the new partial automation of sound engineering is put in place, expected savings in production cost (before tax) are projected as follows: The CFO is concerned that the analysis to date has not really addressed the risk in this project. Your task is to employ scenario and sensitivity analysis to explore how a calculated recommendation might change when subjected to a number of \"what-ifs\". In discussions with CFO, they are confident the initial costs can be kept in a range of + or - \15 of the original estimates. Savings in production costs are less certain because the software will involve new technology that has not been implemented before. An appropriate range of these costs is + or \40 of the original estimates. Required: 1. Calculate the NPV of each alternative based on originally projected costs and savings. 2. Conduct quantitative sensitivity analysis based on the ranges of possible cost estimates and savings. 3. Assess the qualitative risks and rewards of proceeding with this project, and each alternative. As a financial analyst at the Lunchbox Music Studio, you have been asked to evaluate two capital investment alternatives. The company policy has set the cost of capital at \15 for all proposed projects. Lunchbox's usual corporate tax rate is \35. The proposed capital project calls for developing new computer software to facilitate partially automating the sound engineering for recording. Alternative A has initial software development costs projected at \\( \\$ 194,000 \\), while Alternative B would cost \\( \\$ 336,000 \\). Software development costs would be capitalized and qualify for a capital cost allowance (CCA) rate of \30. In addition, IT would hire a software consultant under either alternative to assist in making the decision whether to invest in the project for a fee of \\( \\$ 17,000 \\) and this cost would be expensed when it is incurred. To recover its costs, Lunchbox's IT department would charge the production department for the use of computer time at the rate of \\( \\$ 394 \\) per hour and estimates that it would take 182 hours of computer time per year to run the new software under alternative. Lunchbox owns all its computers and does not currently operate them at capacity. The IT plan calls for this excess capacity to continue in the future. For security reasons, it is company policy not to rent excess computing capacity to outside users. If the new partial automation of sound engineering is put in place, expected savings in production cost (before tax) are projected as follows: The CFO is concerned that the analysis to date has not really addressed the risk in this project. Your task is to employ scenario and sensitivity analysis to explore how a calculated recommendation might change when subjected to a number of \"what-ifs\". In discussions with CFO, they are confident the initial costs can be kept in a range of + or - \15 of the original estimates. Savings in production costs are less certain because the software will involve new technology that has not been implemented before. An appropriate range of these costs is + or \40 of the original estimates. Required: 1. Calculate the NPV of each alternative based on originally projected costs and savings. 2. Conduct quantitative sensitivity analysis based on the ranges of possible cost estimates and savings. 3. Assess the qualitative risks and rewards of proceeding with this project, and each alternative

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Investments

Authors: Zvi Bodie, Alex Kane, Alan Marcus, Stylianos Perrakis, Peter

8th Canadian Edition

007133887X, 978-0071338875

More Books

Students also viewed these Finance questions