Calculating Project Costs Determine the nal price paid by the buyer in these scenarios. a] Cost plus Incentive fee contract: Incentive contracts may be developed
Calculating Project Costs Determine the nal price paid by the buyer in these scenarios. a] Cost plus Incentive fee contract: Incentive contracts may be developed to speed up the completing of a project or reduce buyer costs, consider the data below: Target Cost = $100000 Target Fee = $20000 Target Price = $ 120000 Sharing Ratio 2 70/30 [70% buyer, 30% seller] Actual Cost 2 $ 90000 Additional Fee = Total Fee Paid = Total Project Price =