Capacity of a resource is 2 7 5 hours per week. Average demand on the resource is 2 2 0 hours per week. What is

Capacity of a resource is 275 hours per week. Average demand on the resource is 220 hours
per week. What is the capacity cushion
A)55 hours per week.
B)80 percent.
C)130 percent
D)75 percent.
E)220 hours per week.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business and Administrative Communication

Authors: Kitty o. locker, Donna s. kienzler

10th edition

77830105, 978-0077830106, 978-0073403182

More Books

Students also viewed these General Management questions