Question
Capital Budgeting Decision Criteria: Payback Payback Payback was the earliest -Select-capital structurefinancial statementcapital budgetingCorrect 1 of Item 1 selection criterion. The -Select-NPVMIRRIRRpaybackCorrect 2 of Item
Capital Budgeting Decision Criteria: Payback
Payback Payback was the earliest -Select-capital structurefinancial statementcapital budgetingCorrect 1 of Item 1 selection criterion. The -Select-NPVMIRRIRRpaybackCorrect 2 of Item 1 is a "break-even" calculation in the sense that if a project's cash flows come in at the expected rate, the project will break even. The equation is:
The -Select-shorterlongerCorrect 3 of Item 1 a project's payback, the better the project is. However, payback has 3 main disadvantages: (1) Dollars received in different years are given -Select-lessequalmoreCorrect 4 of Item 1 weight. (2) Cash flows beyond the payback year are ignored. (3) The payback merely indicates when a project's investment is recovered. There is no necessary relationship between a given payback and investor wealth maximization. A variant of the regular payback is the discounted payback. Unlike regular payback, the discounted payback considers -Select-projectcapitaloverheadCorrect 5 of Item 1 costs. However, the discounted payback still disregards cash flows -Select-duringbeforebeyondCorrect 6 of Item 1 the payback year. In addition, there is no specific payback rule to justify project acceptance. Both methods provide information about -Select-profitabilitywealthliquidityCorrect 7 of Item 1 and risk. Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%.
0 | 1 | 2 | 3 | 4 | ||||||
Project A | -950 | 650 | 395 | 240 | 290 | |||||
Project B | -950 | 250 | 330 | 390 | 740 |
What is Project A's payback? Round your answer to four decimal places. Do not round your intermediate calculations. years
What is Project A's discounted payback? Round your answer to four decimal places. Do not round your intermediate calculations. years
What is Project B's payback? Round your answer to four decimal places. Do not round your intermediate calculations. years
What is Project B's discounted payback? Round your answer to four decimal places. Do not round your intermediate calculations. years
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started