Carts Corporation is trying to determine how long it takes for one product to pass through the production process. The following Information was gathered regarding how many days the product spent in various production activities. Activity Inspection Storage Assembly Handling Painting Packaging Tuber of Days 4 3 5 o. Which of the above activities are value-added? b. What is Carts total cycle time? c. Determine Carts' manufacturing efficiency ratio, d-1. If Carts Implements a total quality management program and a just-in-time Inventory system, which of these activities could be eliminated? d-2. If Carts implements a total quality management program and a just-in-time inventory system, what would be the change in Corts manufacturing efficiency ratio? Complete this question by entering your answers in the tabs below. Required A Required Required Required D Determine Carts manufacturing efficiency ratio. (Round your answer to 2 decimal places) Manufacturing concreto Prey 4 of 5 Next > c. Determine Carts' manufacturing efficiency ratlo. d 1. Carts Implements a total quality management program and a just-in-time inventory system which of these activities could be eliminated? d-2. It Carts Implements a total quality management program and a just in time inventory system, what would be the change in Carts manufacturing efficiency ratio? Complete this question by entering your answers in the tabs below. Required A Required B Required Required D 4-1Carts implements a total quality management program and a just in time inventory system, which of these activities could be eliminated d-2. If Carts implements a total quality management program and a just in time Inventory system, what would be the change in Carts manufacturing efficiency ratio (Round your answer to 2 decimal places) Show less d-1 Eliminated activities 0-2 Manufacturing officiency ratio