Case Example: ABC Co . v . XYZ Fireproofing Sub. Statement of Facts On July 9 , 1 9 7 4 , XYZ Fireproofing Sub

Case Example: ABC Co. v. XYZ Fireproofing Sub.
Statement of Facts
On July 9,1974, XYZ Fireproofing Sub entered into a subcontract with prime contractor ABC
Co. to fireproof structural steel as part of the construction of a hospital, in the District of
Columbia, a $100 million project. The subcontract amount was $570,000. Article 2(b) of the
subcontract stated that No such delay caused by reasons beyond the Subcontractors control
shall give rise to any right to the Subcontractor to claim damages therefore from the contractor.
Specification section 9000/6.6 provided that Ducts, piping or conduit or other suspended
equipment that could interfere with the uniform application of the fireproofing material are to be
positioned after the application of the sprayed fireproofing. XYZ Fireproofing Subs work was
disrupted by ABC Co.s delays in ordering and receiving structural steel, from stacking of trades
that caused overcrowding, and when other subcontractors damaged completed work of XYZ
Fireproofing Co. necessitating rework. ABC Co. failed to follow the project schedule because of
the delays in ordering and receiving structural steel that resulted in XYZ Fireproofing Sub.
having to use scaffolding platforms. XYZ Fireproofing Sub had to shift from floor to floor,
rather than completing work on a systematic, scheduled, floor-by floor basis. Further, ABC Co.
did not provide a reasonably clear and convenient work area to XYZ Fireproofing Sub. ABC Co.
failed to reasonably sequence the work to allow XYZ Fireproofing Sub. to perform, and failed to
supervise other subcontractors that ultimately disrupted XYZ Fireproofing Subs work.
Questions:
1. What is a No-Damages for Delay clause in a contract? How does it transfer risk from
an owner to a contractor or from a contractor to a sub-contractor? Discuss.
2. Using the flowchart (Figure 1 below) for making decisions on no-damage-for-delay
clause discuss how the courts would rule in the case provided above? State your
decision with valid reasons.
Fig. 1: Decision flowchart for no-damage-for-delay clause

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management With CompTIA Project+

Authors: Joseph Phillips

4th Edition

9781259860300

More Books

Students also viewed these General Management questions